{"title":"Greylock Site Update","blocks":[{"type":"p","html":"Greylock Site Update - Week Thirty-Two (Week of 10/13)","italic":false,"align":"null"},{"type":"li","html":"Geothermal trench was backfilled","level":0,"ordered":false},{"type":"li","html":"Site lighting was trenched throughout the entire site, roadway areas were encased and backfilled before yesterday’s rain","level":0,"ordered":false},{"type":"li","html":"CMU at the elevator shaft started","level":0,"ordered":false},{"type":"li","html":"Exterior work progressed, level 2 framing started, hunter panels continued, base flashing started","level":0,"ordered":false},{"type":"li","html":"The first deco-rib area of roof was worked on in the west side (see sheet 4)","level":0,"ordered":false},{"type":"p","html":"Greylock Site Update - Week Thirty-One (Week of 10/5)","italic":false,"align":"null"},{"type":"li","html":"Geothermal piping wrapped up and hydrostatic testing was completed","level":0,"ordered":false},{"type":"li","html":"NGrid set utility poles, the last section of primaries were completed and will be encased when we return Tuesday","level":0,"ordered":false},{"type":"li","html":"Site lighting started which is our last big step before paving","level":0,"ordered":false},{"type":"li","html":"Exterior framing and hunter panels made major progress again this week","level":0,"ordered":false},{"type":"li","html":"The last section of SOG (at the crane leaveout) was placed Tuesday","level":0,"ordered":false},{"type":"li","html":"The roofers covered the east half of area A","level":0,"ordered":false},{"type":"p","html":"Greylock Site Update - Week Thirty (Week of 9/28)","italic":false,"align":"null"},{"type":"li","html":"Roofing/exterior framing/sheathing had decent progress, still ramping up","level":0,"ordered":false},{"type":"li","html":"Geothermal circuit piping wrapped up on Friday","level":0,"ordered":false},{"type":"li","html":"The crane leaveout area was prepped for slab on grade","level":0,"ordered":false},{"type":"li","html":"Back of house masonry continued","level":0,"ordered":false},{"type":"li","html":"The ships ladder to the high roof was set, stair 1 detailing continued too","level":0,"ordered":false},{"type":"p","html":"Greylock Site Update - Week Twenty-Nine (Week of 9/21)","italic":false,"align":"null"},{"type":"li","html":"Roofing started this week on area B","level":0,"ordered":false},{"type":"li","html":"Exterior framing in area B is wrapping up today","level":0,"ordered":false},{"type":"li","html":"Pan stairs 2/3 being infilled today, roof curbs/stage ramp and other misc items are being placed too","level":0,"ordered":false},{"type":"li","html":"Our main stair (stair 1) was installed","level":0,"ordered":false},{"type":"li","html":"The site is coming together too, not much left for drainage/utilities","level":0,"ordered":false},{"type":"p","html":"Greylock Site Update - Week Twenty-Eight (Week of 9/14)","italic":false,"align":"null"},{"type":"li","html":"Level 2 slab was placed","level":0,"ordered":false},{"type":"li","html":"Roofing materials were delivered","level":0,"ordered":false},{"type":"li","html":"Exterior framing for area B is about 30%","level":0,"ordered":false},{"type":"li","html":"Roof blocking started in area B","level":0,"ordered":false},{"type":"li","html":"Gravel for pavement prep is 80% and really cleaning the place up","level":0,"ordered":false},{"type":"li","html":"Drainage on the north made major headway too","level":0,"ordered":false},{"type":"p","html":"Greylock Site Update - Week Twenty-Seven (Week of 9/8)","italic":false,"align":"null"},{"type":"li","html":"Roof slab was placed Thursday","level":0,"ordered":false},{"type":"li","html":"Level 2 reinforcing arrived and is partially installed","level":0,"ordered":false},{"type":"li","html":"Masonry started in BOH areas","level":0,"ordered":false},{"type":"li","html":"Exterior framing and roof blocking started","level":0,"ordered":false},{"type":"li","html":"A bunch of utilities advanced (primaries/telcom/sewer/grease trap/geo/drainage)","level":0,"ordered":false},{"type":"li","html":"Crane was on site for glulam again, the tricky tree area was completed","level":0,"ordered":false},{"type":"p","html":"Greylock Site Update - Week Twenty-Six (Week of 8/31)","italic":false,"align":"null"},{"type":"li","html":"Area B detailing was completed today","level":0,"ordered":false},{"type":"li","html":"Stairs 2 and 3 are partially installed","level":0,"ordered":false},{"type":"li","html":"Sleeves/bangits are in on L2, awaiting rebar delivery","level":0,"ordered":false},{"type":"li","html":"Roof mech pads are being prepped for placement","level":0,"ordered":false},{"type":"li","html":"New sewer design is installed","level":0,"ordered":false},{"type":"li","html":"Painter started tnemic paint","level":0,"ordered":false},{"type":"li","html":"Mason mobilized","level":0,"ordered":false},{"type":"p","html":"Greylock Site Update - Week Twenty-Five (Week of 8/24)","italic":false,"align":"null"},{"type":"li","html":"Steel erection is complete.  Sequence 10 wrapped up today","level":0,"ordered":false},{"type":"li","html":"Level 2 deck was turned over, MEP sleeves are installed","level":0,"ordered":false},{"type":"li","html":"Glulam continues, everything is tight and PDC is fighting through it","level":0,"ordered":false},{"type":"li","html":"Temp water/power/lighting all are getting set up in the building","level":0,"ordered":false},{"type":"p","html":"Greylock Site Update - Week Twenty-Four (Week of 8/17)","italic":false,"align":"null"},{"type":"li","html":"Deck/detail has advanced into area B","level":0,"ordered":false},{"type":"li","html":"Glulam beams were set above the cafeteria last week (partially at main entrance too)","level":0,"ordered":false},{"type":"li","html":"Water main leak was found, bacteria testing and turnover week of 8/24","level":0,"ordered":false},{"type":"li","html":"Pressure testing was completed for the geothermal field","level":0,"ordered":false},{"type":"li","html":"Drainage structures were set for URS1 at the far NW corner","level":0,"ordered":false},{"type":"li","html":"Steel sequence 10 expected Wed 8/26","level":0,"ordered":false},{"type":"p","html":"Greylock Site Update - Week Twenty-Three (Week of 8/10)","italic":false,"align":"null"},{"type":"li","html":"Area B steel sequences 11 and 12 were erected in the past day","level":0,"ordered":false},{"type":"li","html":"Area A detailing is pretty far along, studs were shot the past couple days","level":0,"ordered":false},{"type":"li","html":"Glulam beams are coming in Monday for the atrium/cafeteria in Area A","level":0,"ordered":false},{"type":"li","html":"Drainage made major progress again this past week south of the building","level":0,"ordered":false},{"type":"li","html":"Geothermal drilling wrapped up, pressure testing will start Monday","level":0,"ordered":false},{"type":"li","html":"Beam signing went well today, 60+ people showed up from the city","level":0,"ordered":false},{"type":"p","html":"Greylock Site Update - Week Twenty-Two (Week of 8/3)","italic":false,"align":"null"},{"type":"li","html":"Steel is progressing as expected, erecting the middle of the building, detailing the east","level":0,"ordered":false},{"type":"li","html":"A good chunk of drainage was installed underneath the parking lot area","level":0,"ordered":false},{"type":"li","html":"Geothermal loops are close to done, will be wrapping up drilling Monday","level":0,"ordered":false},{"type":"p","html":"Greylock Site Update - Week Twenty-One (Week of 7/27)","italic":false,"align":"null"},{"type":"li","html":"Steel started strong, sequences 1-3 are up, 4 should be too by end of day tomorrow.","level":0,"ordered":false},{"type":"li","html":"Deck/detail is moving along nicely on sequence 1 (north of the gym)","level":0,"ordered":false},{"type":"li","html":"20 bores down for geothermal wells (28 left to go)","level":0,"ordered":false},{"type":"li","html":"Drainage advanced (trailers moved out of the way and then back again for install of redesigned drainage)","level":0,"ordered":false},{"type":"p","html":"Greylock Site Update - Week Twenty (Week of 7/20)","italic":false,"align":"null"},{"type":"li","html":"Area B slab was placed Thursday","level":0,"ordered":false},{"type":"li","html":"Stormwater detention chambers were set for UDS-1 (see sheet 4 logistics, this thing is massive)","level":0,"ordered":false},{"type":"li","html":"The 110t crane for steel is in place and ready for the first truck Monday morning","level":0,"ordered":false},{"type":"li","html":"NFPA 13 test for underground fire service was completed today","level":0,"ordered":false},{"type":"p","html":"Greylock Site Update - Week Nineteen (Week of 7/13)","italic":false,"align":"null"},{"type":"li","html":"Area A slab was placed on Thursday","level":0,"ordered":false},{"type":"li","html":"Horizontal drilling for geothermal wells started, 5 bores were completed","level":0,"ordered":false},{"type":"li","html":"Geothermal piping from the building to the vault was completed/tested","level":0,"ordered":false},{"type":"li","html":"The new fire hydrants finally showed up, chlorination/pressure testing to take place this week to have domestic water service live","level":0,"ordered":false},{"type":"li","html":"Area B slab prep continued, slab to be placed this Thursday","level":0,"ordered":false},{"type":"li","html":"Steel start date solidified for next Monday 7/27","level":0,"ordered":false},{"type":"p","html":"Greylock Site Update - Week Eighteen (Week of 7/6)","italic":false,"align":"null"},{"type":"li","html":"Underground plumbing in area B was completed/inspected","level":0,"ordered":false},{"type":"li","html":"Underslab stone in area A was fine graded","level":0,"ordered":false},{"type":"li","html":"Rigid/vapor barrier/reinforcement in area A started","level":0,"ordered":false},{"type":"li","html":"Area A slab placement to be Thursday 7/16","level":0,"ordered":false},{"type":"li","html":"On track for steel start on 7/20 (date still to be confirmed)","level":0,"ordered":false},{"type":"p","html":"Greylock Site Update - Week Seventeen (Week of 6/29)","italic":false,"align":"null"},{"type":"li","html":"Foundations are complete, stripping wrapped up last week, formwork was loaded out","level":0,"ordered":false},{"type":"li","html":"Underslab electrical and plumbing moved forward, Area A is wrapped up (for the most part)","level":0,"ordered":false},{"type":"li","html":"Underslab stone was placed and rough graded for almost all of Area A, fine grading started too","level":0,"ordered":false},{"type":"li","html":"Slab prep started, diamonds were formed around the columns, rigid/stego arriving today","level":0,"ordered":false},{"type":"li","html":"Geothermal to mobilize this week","level":0,"ordered":false},{"type":"p","html":"Greylock Site Update - Week Fifteen (Week of 6/15)","italic":false,"align":"null"},{"type":"li","html":"Foundation excavation is complete, I’d be surprised if the foundations are not all placed by the end of next week","level":0,"ordered":false},{"type":"li","html":"Underslab electrical and plumbing made major headway this week, conveyor will be used to place underslab stone in the east half of the building next week","level":0,"ordered":false},{"type":"li","html":"The massive grease trap is being set in place today","level":0,"ordered":false},{"type":"li","html":"Sewer RFI halted sewer install this week","level":0,"ordered":false},{"type":"p","html":"Greylock Site Update - Week Fourteen (Week of 6/8)","italic":false,"align":"null"},{"type":"li","html":"South firewall was placed today, crane will move out Monday and remaining footings can be excavated early next week","level":0,"ordered":false},{"type":"li","html":"Domestic service and fire service are tapped on the main and brought into the building","level":0,"ordered":false},{"type":"li","html":"Electrical underground in area A continued","level":0,"ordered":false},{"type":"li","html":"3/4 of the building is filled (brought up to bottom of underslab stone)","level":0,"ordered":false},{"type":"li","html":"Slab materials are arriving late next week","level":0,"ordered":false},{"type":"li","html":"Sewer/drainage will start next week (materials were delivered this week)","level":0,"ordered":false},{"type":"p","html":"Greylock Site Update - Week Thirteen (Week of 6/1)","italic":false,"align":"null"},{"type":"li","html":"North gang form wall is being placed today","level":0,"ordered":false},{"type":"li","html":"Crane moved this morning to the courtyard to strip tomorrow and start building the south firewall","level":0,"ordered":false},{"type":"li","html":"Water main tap and replacement occurred this week","level":0,"ordered":false},{"type":"li","html":"Plenty of backfill occurred this week in area A and courtyard","level":0,"ordered":false},{"type":"li","html":"Underground electrical started in the NE corner at the electrical room","level":0,"ordered":false},{"type":"li","html":"Foundation progress is still moving along, west perimeter wall was placed yesterday","level":0,"ordered":false},{"type":"li","html":"The massive test pit and overexcavation for organics was completed early this week","level":0,"ordered":false},{"type":"p","html":"Greylock Site Update - Week Twelve (Week of 5/25)","italic":false,"align":"null"},{"type":"li","html":"Demo is wrapping up and AEI is demobilizing today","level":0,"ordered":false},{"type":"li","html":"Grading continues on the south half of the site chasing demo out of here","level":0,"ordered":false},{"type":"li","html":"Foundation work is advancing (see sheet 2 for progress)","level":0,"ordered":false},{"type":"li","html":"Underground sanitary was completed in the northeast quadrant (photo on sheet 6)","level":0,"ordered":false},{"type":"li","html":"Elevator pit damproofing was done (photo on sheet 3)","level":0,"ordered":false},{"type":"li","html":"The gang forms for the north firewall are one sided, rebar is partially installed, will be placing the wall mid-week next week (photos on sheet 4 and 7)","level":0,"ordered":false},{"type":"li","html":"Sparkies mobilized yesterday, conduit coming early next week to start underground in the northeast corner","level":0,"ordered":false},{"type":"li","html":"Test pit (where a boring indicated existing deep organics) is in progress (near CL E/8.4), once completed the remainder of foundations can be subgraded","level":0,"ordered":false},{"type":"p","html":"Greylock Site Update - Week Eleven (Week of 5/18)","italic":false,"align":"null"},{"type":"li","html":"Demo and load out has made major headway this past week and is now out of the way of construction (area in red on page 3)","level":0,"ordered":false},{"type":"li","html":"Foundations are moving along (tons of green on page 2).  Some gang forms were stood yesterday for the north firewall between the pre-school and elementary school.","level":0,"ordered":false},{"type":"li","html":"Foundation subgrade and interior fill have progressed nicely too.  Plenty of areas are ready for concrete and underground sanitary piping will be starting next week in the NE corner.","level":0,"ordered":false},{"type":"p","html":"Greylock Site Update - Week Ten (Week of 5/11)","italic":false,"align":"null"},{"type":"li","html":"Concrete is creeping across from the NE towards SW (see page 2 of the attached three week look ahead)","level":0,"ordered":false},{"type":"li","html":"Fire wall rebar was delivered, the crane is expected to arrive mid-week next week","level":0,"ordered":false},{"type":"li","html":"Fill inside the building continues, expecting the plumbers for underground right after memorial day","level":0,"ordered":false},{"type":"li","html":"Area 1 ACM foundations are loaded out, which makes way for the new water main work to start (which will once pricing is approved and materials are delivered, hopefully by the end of next week)","level":0,"ordered":false},{"type":"li","html":"The underground fuel storage tank was removed Tuesday, which allowed the area 3 above ground demo to finish up this week too","level":0,"ordered":false},{"type":"li","html":"The south driveway was developed which will be the new load out area for demo. This eliminates major conflict between construction and demo","level":0,"ordered":false},{"type":"p","html":"Greylock Site Update - Week Eight (Week of 4/27)","italic":false,"align":"null"},{"type":"li","html":"The ground breaking ceremony was a success.  The folks from the city were very happy with how things went.","level":0,"ordered":false},{"type":"li","html":"We had three concrete placements this week.  Footings and walls.  About 150cy total","level":0,"ordered":false},{"type":"li","html":"NGrid removed the guywire and lights from the building so area 3 (of 3) above grade demo started","level":0,"ordered":false},{"type":"li","html":"ACM foundation demo started today.  Half of area 1 was stockpiled","level":0,"ordered":false},{"type":"li","html":"Fill in the building footprint started, will be ready for interior piers next week","level":0,"ordered":false},{"type":"p","html":"Greylock Site Update - Week Seven (Week of 4/20)","italic":false,"align":"null"},{"type":"li","html":"A large chunk of the east footings were prepped","level":0,"ordered":false},{"type":"li","html":"Footing formwork chased","level":0,"ordered":false},{"type":"li","html":"First delivery of rebar arrived Thursday","level":0,"ordered":false},{"type":"li","html":"Had a rebar inspection with building inspector this afternoon","level":0,"ordered":false},{"type":"li","html":"Will be placing a section of footings mid-day Monday","level":0,"ordered":false},{"type":"li","html":"Demo continued, major haul out of debris this week","level":0,"ordered":false},{"type":"li","html":"Topsoil strip continued, major haul out of topsoil also","level":0,"ordered":false},{"type":"li","html":"We received approval to start removing ACM foundations","level":0,"ordered":false},{"type":"p","html":"Greylock Site Update - Week Six (Week of 4/13)","italic":false,"align":"null"},{"type":"li","html":"Demolition is cruising (area 1 and half area 2 above grade are down, loadout early next week)","level":0,"ordered":false},{"type":"li","html":"Site is shaping up, water is shedding nicely, topsoil is being loaded out, construction roadway has advanced","level":0,"ordered":false},{"type":"li","html":"The building was located by the surveyor and control was added","level":0,"ordered":false},{"type":"li","html":"A stretch of footings are stoned and ready for ledgerboard and rebar","level":0,"ordered":false},{"type":"li","html":"The concrete crew mobilized today, established their control, received materials","level":0,"ordered":false},{"type":"p","html":"Greylock Site Update - Week Five (Week of 4/6)","italic":false,"align":"null"},{"type":"li","html":"Demolition kicked off today","level":0,"ordered":false},{"type":"li","html":"Rebar was released (expected Mon 4/20 (to be confirmed))","level":0,"ordered":false},{"type":"li","html":"Area 3 (of 3) interior and exterior asbestos abatement wrapped up","level":0,"ordered":false},{"type":"li","html":"North driveway was established","level":0,"ordered":false},{"type":"li","html":"Temp fence finished up, some scrim was hung today","level":0,"ordered":false},{"type":"li","html":"Topsoil was stripped from most of the building footprint, ready for excavation next week ahead of footings","level":0,"ordered":false},{"type":"li","html":"Little (but PITA) things were taken care of – demo permit / temp water / concession stand demo","level":0,"ordered":false},{"type":"p","html":"Greylock Site Update - Week Four (Week of 3/30)","italic":false,"align":"null"},{"type":"li","html":"Area 3 (of 3) interior abatement will wrap up early next week","level":0,"ordered":false},{"type":"li","html":"Area 1 &amp; 2 exterior openings abatement will be done Mon","level":0,"ordered":false},{"type":"li","html":"Parking lots and basketball court were milled Wed","level":0,"ordered":false},{"type":"li","html":"North driveway has started (could land a plane on this thing!)","level":0,"ordered":false},{"type":"li","html":"Fencelines are established.  Trailers were delivered","level":0,"ordered":false},{"type":"li","html":"Demolition will start Tue/Wed","level":0,"ordered":false},{"type":"li","html":"Building permit was picked up this week","level":0,"ordered":false},{"type":"li","html":"Waiting on rebar approval for fabrication then it’s off to the races!","level":0,"ordered":false},{"type":"p","html":"Greylock Site Update - Week Three (Week of 3/23)","italic":false,"align":"null"},{"type":"li","html":"Area 2 abatement / visual inspection was completed today, air testing to be Monday","level":0,"ordered":false},{"type":"li","html":"Area 3 abatement pre-inspection to be Monday","level":0,"ordered":false},{"type":"li","html":"3/4 of the fence posts are driven, chain link started today","level":0,"ordered":false},{"type":"li","html":"Topsoil was stripped on the west side (between Phelps and the existing school)","level":0,"ordered":false},{"type":"li","html":"Above ground structures were removed (dugouts/play structures/foul poles/etc)","level":0,"ordered":false},{"type":"li","html":"Temp power is close to completion, to be inspected by the city Monday","level":0,"ordered":false},{"type":"li","html":"Things are coming together to have demo start Mon 4/6.  AEI dropped off their 480s","level":0,"ordered":false},{"type":"li","html":"Rebar shops were sent to us an hour ago from Marguerite!","level":0,"ordered":false},{"type":"p","html":"Greylock Site Update - Week Two (Week of 3/16)","italic":false,"align":"null"},{"type":"li","html":"Area 1 abatement / inspection / air testing was completed Friday","level":0,"ordered":false},{"type":"li","html":"Area 2 pre-abatement inspection was Friday morning","level":0,"ordered":false},{"type":"li","html":"Stumps were removed, temp fenceline was grubbed","level":0,"ordered":false},{"type":"li","html":"Erosion control started, silt fence half done","level":0,"ordered":false},{"type":"li","html":"Temp power utility pole was set / Appalachian trail kiosk was relocated","level":0,"ordered":false},{"type":"li","html":"Building permit application to be submitted Monday","level":0,"ordered":false},{"type":"p","html":"Greylock Site Update - Week One (Week of 3/9)","italic":false,"align":"null"},{"type":"li","html":"Area 1 abatement prep started Mon / abatement started Thurs","level":0,"ordered":false},{"type":"li","html":"DEP did an abatement inspection mid-day Thurs, AEI performed well, nothing to note","level":0,"ordered":false},{"type":"li","html":"Abatement trailer #1 was fully loaded by the end of day Friday","level":0,"ordered":false},{"type":"li","html":"Trees were removed Tues / chipped into trailers Wed / logs loaded out Thurs","level":0,"ordered":false},{"type":"li","html":"Gas service was removed on Tuesday","level":0,"ordered":false},{"type":"li","html":"Building inspector agreed to splitting building which allows demo to start before electrical service removal.","level":0,"ordered":false},{"type":"li","html":"Owner and design team are ok with removing the salvaged door portals from the project.","level":0,"ordered":false}]}